Upcoming Construction Project on Elmwood Drive

Posted on May 7, 2026 in PSA

Location: Between Lewisville Boulevard and Massey Avenue

Date: Mid-May until late Fall

Work details: A full road reconstruction along with improvements to pedestrian infrastructure and intersections are also planned, making for an improved experience while travelling through the area.

Below is a tentative schedule, which may be subject to change:

  • May 19 to 22: Complete watermain connections within the Lewisville Road intersection, where lane reductions will be necessary.
  • May 25 to June 30: Complete watermain renewal, traffic signals renewals and some storm sewer repairs between Lewisville Road and Donald Avenue.
  • June 29 to July 1: Base asphalt paving from Lewisville Road to Donald Avenue
  • June 22 to mid October: Complete watermain renewal, sanitary sewer renewals and storm sewer extensions between Donald Avenue and Massey Avenue.
  • Mid October to Mid November: Asphalt paving, multi-purpose trail installation (Lewisville Road to Donald Avenue) and final restorations between Lewisville Road and Massey Avenue.

In total, crews will install approximately 505 meters of watermain,185 metres of new storm system, 300 metres of renewed sanitary lines, and install new traffic signals infrastructure.

Traffic impact: Work will be carried out in phases, with each phase affecting both vehicle and pedestrian access differently. The City will issue public service announcements in advance of each new phase to keep residents and commuters informed. 

A reminder to remain cautious of crews at work and be patient while travelling through the area.